Construction certificates determined in Ballina Shire Council, week of 6 April 2026
7 construction certificates were determined in Ballina Shire Council between Monday 6 April 2026 and Sunday 12 April 2026, the same as the week before. Councils add records for several weeks; this count was last updated 20 November 2026, 4:33 am Sydney time.
Determined this week
| Determined | Address | Cost | Builder | Application |
|---|---|---|---|---|
| 10 Apr 2026 | 11 SUZANNE STREET EAST BALLINA 2478East Ballina | $33,000 | ZAC MAKIN | CFT-921038 |
| 9 Apr 2026 | 23 QUAYS DRIVE WEST BALLINA 2478West Ballina | $805,258 | UNIQUE VIEW HOMES PTY LTD | CFT-933477 |
| 9 Apr 2026 | 150 SNEATHS ROAD WOLLONGBAR 2477Wollongbar | $30,000 | MAKIN' SHEDS PTY LIMITED | CFT-920370 |
| 9 Apr 2026 | 5 WEJUBA GARDENS BALLINA 2478Ballina | $6,615 | CFT-910026 | |
| 9 Apr 2026 | 114 EYLES DRIVE EAST BALLINA 2478East Ballina | $131,500 | CFT-898954 | |
| 8 Apr 2026 | 56 STEWART STREET LENNOX HEAD 2478Lennox Head | $3,381,474 | TWIL CONSTRUCTIONS PTY LTD | CFT-876903 |
| 7 Apr 2026 | 6 DARCEY AVENUE CUMBALUM 2478Cumbalum | $19,500 | CFT-921315 |
By category
| Category | Determined |
|---|---|
| Demolition | 4 |
| Dwelling house | 4 |
| Alterations and additions | 3 |
| Shed, garage or carport | 2 |
| Swimming pool | 2 |
| Deck, patio or verandah | 1 |
A certificate can be counted under more than one category.
Previous week, 30 March 2026 · Next week, 20 April 2026
What a construction certificate is
A construction certificate confirms that the detailed building plans comply with the Building Code of Australia and the development consent. Building work approved by a development application cannot start until one is issued, and the Planning Portal feed marks a decided certificate Determined.