Construction certificates determined in Orange City Council, week of 24 August 2026
9 construction certificates were determined in Orange City Council between Monday 24 August 2026 and Sunday 30 August 2026, up 80% on the week before. Councils add records for several weeks; this count was last updated 20 November 2026, 4:33 am Sydney time.
Determined this week
| Determined | Address | Cost | Builder | Application |
|---|---|---|---|---|
| 28 Aug 2026 | 227 MCLACHLAN STREET ORANGE 2800Orange | $2,128,815 | I C R ENGINEERING PTY LTD | CFT-973632 |
| 27 Aug 2026 | 42 BUCKLAND DRIVE ORANGE 2800Orange | $420,000 | CFT-1000544 | |
| 26 Aug 2026 | 6 DON PETERS PLACE CLIFTON GROVE 2800Clifton Grove | $63,000 | DANIEL TYACK BUILDING AND CONSTRUCTION PTY LTD | CFT-979623 |
| 26 Aug 2026 | 1 SIMPSON CLOSE ORANGE 2800Orange | $26,510 | DANIEL B & JENNIFER A KING, trading as ADDSPAN | CFT-973939 |
| 26 Aug 2026 | 7 NATIONAL AVENUE ORANGE 2800Orange | $1,200,000 | JOHN NUNN BUILDING CONTRACTORS PTY LIMITED, trading as John Nunn Building Contractors Pty Ltd | CFT-961635 |
| 25 Aug 2026 | 50 MARCH STREET ORANGE 2800Orange | $389,616 | COLIN JOSS & CO. PTY. LIMITED, trading as COLIN JOSS & CO PTY LIMITED | CFT-912588 |
| 24 Aug 2026 | 5 COVENT CLOSE ORANGE 2800Orange | $11,000 | The trustee for The Gersbach Family Trust, trading as GARAGE WORLD - CENTRAL WEST | CFT-999010 |
| 24 Aug 2026 | 288 HINEY ROAD SPRING CREEK 2800Spring Creek | $120,997 | WSL CONSTRUCTIONS PTY LTD | CFT-992509 |
| 24 Aug 2026 | 107 CLINTON STREET ORANGE 2800Orange | $694,700 | CFT-1001167 |
By category
| Category | Determined |
|---|---|
| Alterations and additions | 6 |
| Dwelling house | 4 |
| Shed, garage or carport | 4 |
| Apartments and multi-dwelling | 1 |
| Demolition | 1 |
| Industrial and warehouse | 1 |
| Subdivision | 1 |
| Swimming pool | 1 |
A certificate can be counted under more than one category.
Previous week, 17 August 2026 · Next week, 31 August 2026
What a construction certificate is
A construction certificate confirms that the detailed building plans comply with the Building Code of Australia and the development consent. Building work approved by a development application cannot start until one is issued, and the Planning Portal feed marks a decided certificate Determined.