Construction certificates determined in Penrith City Council, week of 28 September 2026

12 construction certificates were determined in Penrith City Council between Monday 28 September 2026 and Sunday 4 October 2026, up 71% on the week before. Councils add records for several weeks; this count was last updated 20 November 2026, 4:33 am Sydney time.

Determined this week

DeterminedAddressCostBuilderApplication
2 Oct 202632 DHIMAN STREET CLAREMONT MEADOWS 2747Claremont Meadows$850,000IDP NSW PTY LTDCFT-1034597
2 Oct 202660-64 COPELAND STREET KINGSWOOD 2747Kingswood$460,000CLASSIC GROUP PTY LTDCFT-1031734
2 Oct 202643 CASTLEREAGH STREET PENRITH 2750Penrith$15,800CFT-1020013
1 Oct 202610 Aberfeldy Rd, Orchard Hills NSW 2748Orchard Hills$500,000SAREEN PROPERTY GROUP PTY LTDCFT-1025296
1 Oct 20269 GAUGE STREET WERRINGTON 2747Werrington$2,517,312PRIME PROJECTS CO PTY LTDCFT-1003493
30 Sep 202610A COCORA STREET EDEN 2551Eden$19,880CFT-973481
30 Sep 2026754 MAMRE ROAD KEMPS CREEK 2178Kemps Creek$39,592,650THE TRUSTEE FOR QANSTRUCT (AUST) UNIT TRUST, trading as QANSTRUCT (AUST) UNIT TRUSTCFT-1038923
30 Sep 2026390 CADDENS ROAD CLAREMONT MEADOWS 2747Claremont Meadows$638,035CFT-1036959
30 Sep 202694-100 EXPLORERS WAY ST CLAIR 2759St Clair$49,968,493LIPMAN PTY. LTD.CFT-1026912
30 Sep 202615 HUDDLESTON STREET COLYTON 2760Colyton$880,088BD BUILD PTY LTDCFT-1016854
29 Sep 20262B PEARTREE CIRCUIT WERRINGTON$539,910EDEN BRAE HOLDINGS PTY LIMITEDCFT-966444
28 Sep 202620 GEORGE STREET KINGSWOOD 2747Kingswood$1,365,700CFT-1033920

By category

CategoryDetermined
Dwelling house6
Alterations and additions3
Dual occupancy2
Apartments and multi-dwelling1
Commercial1
Deck, patio or verandah1
Demolition1
Industrial and warehouse1
Secondary dwelling1
Subdivision1

A certificate can be counted under more than one category.

2 more have no category from this list.

Previous week, 21 September 2026 · Next week, 5 October 2026

What a construction certificate is

A construction certificate confirms that the detailed building plans comply with the Building Code of Australia and the development consent. Building work approved by a development application cannot start until one is issued, and the Planning Portal feed marks a decided certificate Determined.